0

Richard and Damian Taylor. Contract Law Directions (2019 7 ed). BAILII has Alfred McAlpine Construction Limited v. Panatown Limited [2000] UKHL 43. p 349.

Benefits in construction contracts

The House of Lords confirmed in the complex case of Alfred McAlpine v Panatown (2001) that, outside the social/consumer contracts where the contract is made by one party for the benefit of others as a matter of convenience and simplicity, there is no general rule allowing a contracting party to recover a loss on behalf of a third party.

McAlpine contracted with Panatown to construct a building on land owned by UIPL, a company in the same group as Panatown. McAlpine also provided a ‘duty of care deed’ to UIPL directly whereby they agreed to use all reasonable skill, etc. in constructing the building.

p 350

The project did not go well and the costs of repairs for the alleged defects plus damages for delay were estimated to be tens of millions of pounds. The decision was made by the group of companies to sue under the main contract between McAlpine and Panatown rather than under the duty of care deed between McAlpine and UIPL. [I boldened.] McAlpine argued that Panatown, as opposed to UIPL who was the owner of the defective building, had suffered no loss. Panatown argued in the House of Lords: (i) that it was entitled to recover the loss suffered by UIPL on its behalf; and (ii) that in any event it had suffered a loss itself in that it had not received what it bargained for even if it was itself financially no worse off.

enter image description here

On the first point relating to recovery of loss suffered by a third party, the House of Lords was clear, as has already been said, that there was no general rule permitting such recovery. The real issue here however was whether Panatown could rely on a special rule traceable back to Dunlop v Lambert in 1839 and referred to in The Albazero (1977) by Lord Diplock in relation to contracts for the carriage of goods. This rule was then developed by the House of Lords in Linden Gardens v Lenesta (1994) so as to apply to contracts for the construction of a building.

The Dunlop v Lambert/Albazero exception applies to contracts whereby the claimant is the original consignor of goods to the defendant carrier, it being contemplated that the ownership of the goods will be transferred on by the claimant to subsequent purchasers whilst still being carried by the defendant. The subsequent purchasers are therefore the ones who are, by the time of the breach, the owners who suffer the actual loss or damage to the goods but who have no contract with the defendant carrier. The exception recognizes that the claimant can recover damages even though he suffers no loss personally and that he holds the damages on behalf of the subsequent purchasers who have suffered loss.

This exception was applied by the House of Lords in Linden Gardens v Lenesta (1993), or more accurately in the second case heard and reported with that case, St Martin’s Property Corporation v McAlpine.

2
  • I need more context - don’t understand the party’s roles in the arrangement
    – Dale M
    Nov 17, 2019 at 10:41
  • @DaleM Thanks. I quoted more from the textbook. You see my link to BAILII right?
    – user89
    Nov 18, 2019 at 7:18

1 Answer 1

1

Ewan McKendrick's The Common Law at Work: The Saga of Alfred McAlpine Construction Ltd v Panatown Ltd answers your question at p. 151.

      The defects alleged to exist in the works presented the Unex Group with the need to make a decision. They had two principal potential means of redress. The first was for Panatown to sue McAlpine for breach of the building contract and the second was for UIPL to sue McAlpine for breach of the duty of care deed. Neither route was free from difficulty. With the benefit of hindsight, we can see that the most obvious difficulty with the first route lay in demonstrating that Panatown had suffered a loss as a result of McAlpine’s alleged breaches of contract.25 But in other respects, a contractual claim by Panatown appeared advantageous. In the first place, the contract contained an arbitration clause and so could be resolved before an arbitrator without McAlpine being able to join numerous subcontractors to the proceedings. Secondly, the rights contained in the contract were more extensive than those to be found in the duty of care deed: the contract contained a number of strict obligations and also made provision for the payment of liquidated damages for delay. Thirdly, Alfred McAlpine plc, the holding company of McAlpine, had entered into a parent company guarantee with Panatown under which it agreed to guarantee due performance of the contract by its subsidiary, McAlpine.

He didn't break a new para, but I do so to make reading easier.

On the other hand, the advantage of a claim under the duty of care deed was that UIPL did not appear to have any difficulty in establishing that it had suffered a loss as a result of the alleged breaches of duty by McAlpine. But in other respects a claim under the duty of care deed was more hazardous. In particular, the duty of care deed did not contain an arbitration clause, the duty assumed by McAlpine under the deed was not strict but only to exercise reasonable care and skill and UIPL did not have the benefit of a parent company guarantee by Alfred McAlpine plc. Thus it was decided by the Unex group that Panatown should bring proceedings against McAlpine, invoking the arbitration clause contained in that contract. Notice of arbitration was given by Panatown on 8 July 1992, prior to the determination of the contract between Panatown and McAlpine.

You must log in to answer this question.