2

A is a book publisher and would like to take part in a Book Fair. A contracted B to do all the arrangements, for example, erecting displays and stands in the venue of the Fair. A agreed to pay B by two instalments.

The payment of the second instalment is late for 4 days. B attempted to terminate the contract, claiming that A has committed a 'repudiatory breach ' of the contract by late payment and that time is the essence of the contract.

Assuming that time is actually NOT a condition (or essence) of the contract, and thus B in fact has NO right to terminate, would B's attempt to terminate amount to an anticipatory breach? Because B has clearly evinced an intention to refuse all performance by 'terminating' the contract?

1 Answer 1

1

There are 2 easy ways to terminate a contract: by performance or by agreement. All the other ways are difficult, painful and expensive.

The only way to know if you have a right to terminate is do it, get sued and have a judge tell you you did have that right ... or not.

A and B should talk to each other and work out a way to either complete the contract (i.e. renegotiate) or work out how to end it in the least painful way possible.

You must log in to answer this question.

Not the answer you're looking for? Browse other questions tagged .